Tesla tech support and my installer have confirmed that the voltage coming in to my house from the grid is too high (>260v) and this is causing my battery to go in to standby mode and can also be dangerous if not rectified.
Can you please let me know how I report this issue and get it resolved.
AGL are retailers and only collect payments for Electricity that you purchase from them and feed-in.
Your Electrician should have informed you that your Supplier (listed on your bill) is responsible for the voltage on your line.
If the voltage is greater than 260 volts (255 is normally accepted as the max by the way) I am surprised that devices in your residence have not failed.
Phone your supplier and get this issued now.
At this voltage your INVERTER should also shut down, meaning that you will not be generating any solar feed-in.
i have just installed solar panel with inverter. Since installation there has been an inverter shutdown daily or twice a day. Who is responsible to resolve this issue? The installler or the company I signed the contract with?
Hi @OP, as already suggested we are responsible for billing, and while we do arrange with distributors to arrange for meter upgrading, they are responsible for owning and maintaining that infrastructure. If you haven't already, I would contact a qualified professional to take a look, and contact your distributor to get pointed in the right direction to get this resolved! Regards- Mark
Accepted Solution
NeilC
+22 more
Powerhouse
•
4 years ago
@OP
AGL are retailers and only collect payments for Electricity that you purchase from them and feed-in.
Your Electrician should have informed you that your Supplier (listed on your bill) is responsible for the voltage on your line.
If the voltage is greater than 260 volts (255 is normally accepted as the max by the way) I am surprised that devices in your residence have not failed.
Phone your supplier and get this issued now.
At this voltage your INVERTER should also shut down, meaning that you will not be generating any solar feed-in.
2
1
_Mark_
+16 more
AGL Moderator
•
4 years ago
Hi @OP, as already suggested we are responsible for billing, and while we do arrange with distributors to arrange for meter upgrading, they are responsible for owning and maintaining that infrastructure. If you haven't already, I would contact a qualified professional to take a look, and contact your distributor to get pointed in the right direction to get this resolved! Regards- Mark
0
0